PROJECT UPDATES



IMG_3270

IMG_3271

IMG_3268

IMG_3270
1/4
WEEK SEVEN

New Bathroom

Player Corridor

9.7-9.27 Pistons Lkr Rm 3WK

New Bathroom
1/11
OVERVIEW:
-
Drywall finishing completed this week.
-
Ceiling framing and above ceiling MEP ongoing.
-
Tile complete in both new toilet rooms.
-
Painting above ceilings today and tomorrow, and will move to walls next week.
-
Tile starts in hydrotherapy next week.
-
Drywall ceilings starting today.
-
Low voltage cabling started this week.

IMG_3270

IMG_3271

IMG_3268

IMG_3270
1/4
WEEK SIX

Video Room

New Entry Hall

8.31-9.20 Pistons Lkr Rm 3WK

Video Room
1/10
OVERVIEW:
-
Drywall hanging is almost complete.
-
Drywall finishing is underway.
-
Floor tile started today.
-
HVAC rough inspection passed.
-
Mod final field measured for millwork panels.
-
MEP is ongoing above ceiling.
-
Fire suppression rough is complete, with a hydro test scheduled for next week.

IMG_3270

IMG_3271

IMG_3268

IMG_3270
1/4
WEEK FIVE

New Entry Hall

Video Room

8.24-9.13 Pistons Lkr Rm 3WK

New Entry Hall
1/5
OVERVIEW:
-
Received rough in-wall plumbing approval
-
Received rough in-wall electrical approval
-
Received rough framing approval, pending the repair of a handful of existing fireproofing and penetrations noted by the inspector
-
Completed in-wall backing for the mounting of devices, signs, screens, etc
-
Completed onsite coordination walk-throughs with the signage vendor and AV vendor
WEEK FOUR

Massage Room

Player Entrance

8.17-9.6 Pistons Lkr Rm 3WK

Massage Room
1/7
OVERVIEW:
-
Rough framing continued
-
Door frames received and installed
-
MEP Trades moving along with rough-in / Inspections next week
WEEK THREE

New Entry Hall 1

New Entry Hall 2

8.24-9.13 Pistons Lkr Rm 3WK

New Entry Hall 1
1/4
OVERVIEW:
-
Rough framing started
-
Underground plumbing completed & inspected by City
-
Concrete slab infill poured
-
Demolition winding down
WEEK TWO

Locker Room

Hydrotherapy

8.3-8.23 Pistons Lkr Rm 3WK

Locker Room
1/4
OVERVIEW:
-
85% Hydro Therapy Room tile demolition completed
-
Scarifying existing floors and started saw cutting for underground
-
Electricians moving along with demo crews
-
Carpenters mobilized
WEEK ONE

Training

Locker Room

7.27-8.16 Pistons Lkr Rm 3WK (002)

Training
1/4
OVERVIEW:
-
Demolition started
-
Temp. Protection set-up
-
Power disconnected
-
Fire alarm & security devices removed
-
Ceilings and lockers removed