PROJECT UPDATES

White_FRS_Outlined_Square.png
whiteHOK_Rossetti_Logo_Lockup.png

WEEK NINE

OVERVIEW:

  • Ceiling grid installation is complete and inspected

  • Ceiling tile installation is ongoing

  • Paint is ongoing

  • Locker installation will complete this weekend

  • Wall panel installation will start tomorrow

  • Bathroom vanities have been set

  • Lighting installation ongoing

  • Hydrotherapy tile installation is complete

  • LED wall installation is complete and tested

  • Duct cleaning is complete

WEEK EIGHT

OVERVIEW:

  • Hydrotherapy ceiling finished and painted, wall tile underway

  • Locker room drywall ceiling finished

  • Last of drywall ceilings wrapping up

  • Training room wall graphic removed, and wall repaired and finished for new graphic

  • Training room ceiling modifications completed

  • Millwork cleating and base started

  • Priming and painting ongoing

  • Electrical and AV ongoing

WEEK SEVEN

OVERVIEW:

  • Drywall finishing completed this week.

  • Ceiling framing and above ceiling MEP ongoing.

  • Tile complete in both new toilet rooms.

  • Painting above ceilings today and tomorrow, and will move to walls next week.

  • Tile starts in hydrotherapy next week.

  • Drywall ceilings starting today.

  • Low voltage cabling started this week. 

WEEK SIX

OVERVIEW:

  • Drywall hanging is almost complete.
  • Drywall finishing is underway.
  • Floor tile started today.
  • HVAC rough inspection passed.
  • Mod final field measured for millwork panels.  
  • MEP is ongoing above ceiling.
  • Fire suppression rough is complete, with a hydro test scheduled for next week. 

WEEK FIVE

OVERVIEW:

  • Received rough in-wall plumbing approval
  • Received rough in-wall electrical approval
  • Received rough framing approval, pending the repair of a handful of existing fireproofing and penetrations noted by the inspector
  • Completed in-wall backing for the mounting of devices, signs, screens, etc
  • Completed onsite coordination walk-throughs with the signage vendor and AV vendor

WEEK FOUR

OVERVIEW:

  • Rough framing continued
  • Door frames received and installed
  • MEP Trades moving along with rough-in / Inspections next week

WEEK THREE

OVERVIEW:

  • Rough framing started
  • Underground plumbing completed & inspected by City
  • Concrete slab infill poured
  • Demolition winding down

WEEK TWO

OVERVIEW:

  • 85% Hydro Therapy Room tile demolition completed
  • Scarifying existing floors and started saw cutting for underground
  • Electricians moving along with demo crews
  • Carpenters mobilized

WEEK ONE

OVERVIEW:

  • Demolition started
  • Temp. Protection set-up
  • Power disconnected
  • Fire alarm & security devices removed
  • Ceilings and lockers removed

NAVIGATE

CONTACT

Trans_FRS_Square.png

FRANK REWOLD & SONS INC.

303 E. Third Street, Suite 300

Rochester, MI 48307 

248.651.7242

  • White Facebook Icon
  • White LinkedIn Icon
  • White Twitter Icon
  • White Instagram Icon
  • White YouTube Icon

@frankrewoldsons

Copyright © 2026 Frank Rewold & Sons Inc.

CONNECT WITH US!

Thanks for submitting!

bottom of page