PROJECT UPDATES






WEEK NINE




OVERVIEW:
-
Ceiling grid installation is complete and inspected
-
Ceiling tile installation is ongoing
-
Paint is ongoing
-
Locker installation will complete this weekend
-
Wall panel installation will start tomorrow
-
Bathroom vanities have been set
-
Lighting installation ongoing
-
Hydrotherapy tile installation is complete
-
LED wall installation is complete and tested
-
Duct cleaning is complete




WEEK EIGHT




OVERVIEW:
-
Hydrotherapy ceiling finished and painted, wall tile underway
-
Locker room drywall ceiling finished
-
Last of drywall ceilings wrapping up
-
Training room wall graphic removed, and wall repaired and finished for new graphic
-
Training room ceiling modifications completed
-
Millwork cleating and base started
-
Priming and painting ongoing
-
Electrical and AV ongoing




WEEK SEVEN




OVERVIEW:
-
Drywall finishing completed this week.
-
Ceiling framing and above ceiling MEP ongoing.
-
Tile complete in both new toilet rooms.
-
Painting above ceilings today and tomorrow, and will move to walls next week.
-
Tile starts in hydrotherapy next week.
-
Drywall ceilings starting today.
-
Low voltage cabling started this week.
WEEK SIX




OVERVIEW:
-
Drywall hanging is almost complete.
-
Drywall finishing is underway.
-
Floor tile started today.
-
HVAC rough inspection passed.
-
Mod final field measured for millwork panels.
-
MEP is ongoing above ceiling.
-
Fire suppression rough is complete, with a hydro test scheduled for next week.
WEEK FIVE




OVERVIEW:
-
Received rough in-wall plumbing approval
-
Received rough in-wall electrical approval
-
Received rough framing approval, pending the repair of a handful of existing fireproofing and penetrations noted by the inspector
-
Completed in-wall backing for the mounting of devices, signs, screens, etc
-
Completed onsite coordination walk-throughs with the signage vendor and AV vendor
WEEK FOUR




OVERVIEW:
-
Rough framing continued
-
Door frames received and installed
-
MEP Trades moving along with rough-in / Inspections next week
WEEK THREE




OVERVIEW:
-
Rough framing started
-
Underground plumbing completed & inspected by City
-
Concrete slab infill poured
-
Demolition winding down
WEEK TWO




OVERVIEW:
-
85% Hydro Therapy Room tile demolition completed
-
Scarifying existing floors and started saw cutting for underground
-
Electricians moving along with demo crews
-
Carpenters mobilized
WEEK ONE




OVERVIEW:
-
Demolition started
-
Temp. Protection set-up
-
Power disconnected
-
Fire alarm & security devices removed
-
Ceilings and lockers removed